Project Name:
Reactor Cooling Loop Acid Cleaning & Passivation and Tank Cleaning and
What We Do
Subcontract under NPS Engineering & Construction co.,ltd.
- Tank Cleaning, Toluene disposal, Tank 006T18 (Dia. 34 m. x H 18 m.) Close-loop cleaning to control released hydrocarbon <=1%, L.E.L.=0% and VOCs <= 500 ppm.)
Start date : Feb 16, 2017 Completed : Feb 18 , 2017
- Reactors no. 11.304C & 11.304D Cooling loop Acid cleaning & Passivation
Start date : Mar 19, 2017 Completed : Mar 21 , 2017



What We Do
Subcontract under NPS Engineering & Construction co.,ltd.
- Tank Cleaning, Toluene disposal, Tank 006T18 (Dia. 34 m. x H 18 m.) Close-loop cleaning to control released hydrocarbon <=1%, L.E.L.=0% and VOCs <= 500 ppm.)
Start date : Feb 16, 2017 Completed : Feb 18 , 2017 - Reactors no. 11.304C & 11.304D Cooling loop Acid cleaning & Passivation
Start date : Mar 19, 2017 Completed : Mar 21 , 2017